If job a-200 consists of 50 units what is the average cost


a) Weaver Company's predetermined overhead rate is $18.00 per direct labor-hour and its direct labor wage rate is $12.00 per hour. The following information pertains to Job A-200:
Direct materials ........$200
Direct labor ...........$120

Required:

1. What is the total manufacturing cost assigned to Job A-200?
2. If Job A-200 consists of 50 units, what is the average cost assigned to each unit included in the job?