If bcwp500 bcws600 acwp400 and eac900 what is project cost


If BCWP=$500, BCWS=$600, ACWP=$400 and EAC=$900, what is project cost and schedule status? a. under budget, behind schedule b. over budget, behind schedule c. over budget, ahead of schedule d. under budget, ahead of schedule.