True/False
1. If an activity has multiple predecessors, its late start is determined by the latest finish of its predecessors.
2. The total slack of each of the activities on a sub path will be the same as the total slack of the other activities on the sub path.
3. The free slack of each of the activities on a sub path will be the same as the free slack of the other activities on the sub path.