If a transformer steps the voltage down from 8800 V (at the pole) to 120 V (at the building) and it is to deliver 1000 kW to the building at 80% efficiency, what is the current in the primary, what is the currnet in the secondary, and what is the ratio of primary turns to secondary turns?