1. If a project's NPV is greater than zero, then the
A - project adds value to the firm
B - project destroys firm value
C - investment is also greater than the present value of cash flows
D - project does not increase shareholders wealth
2. The discount rate used to determine the net present value of a project is the
A- CAPM return
B- risk-free rate of interest
C- cost of debt
D- cost of capital of the firm
3. Which of the following statements are correct?
A - if a project's NPV is less than zero, then its IRR must be less than the WACC
B - the lower the WACC used to calculate a project's NPV, the lower the calculated NPV will be
C - if a project's NPV s greater than zero, then its IRR must be less than zero
D - The NPV of a relatively low-risk project should be found using a relatively high WACC.