Identifying and calculating the critical path


Question: When identifying and calculating the critical path, which is the most important item to identify? Multiple Choice the sequence of tasks that require the most resources and materials the tasks that cost the most money to complete the sequence of tasks that take the longest time to complete the sequence of tasks that take the shortest time to complete the sequence of tasks that take the most worker effort to complete