You are managing a project to film 5 promotional videos to be posted on YouTube, to promote one of the UI fraternities. Your project jas a BAC of $12,000. One of the tasks on the the critical path is to arrange fililming locations. The task has a BAC of $2,000. You have confirmed 4 of the 10 locations. The task is scheduled to take 2 weeks(10 days), and it is the end of day 2. You have spent $300 so far.
a. Identify the task's BAC, AC, EV and PV
b. Calculate SPI and CPI
c. What do the results tell you about the task's schedule and budget?