Identify the ONE response that is NOT a characteristic of a project.
A) A project has a set of defined set of deliverables and a timeline.
B) A project is only performed by subject matter experts
C) A project has a defined start and end date
D) A project enables a project team to be focused on a dedicated activity for a specific period of time to produce a specific result for a customer.