A plant start-up is based on the following network:
Immediate Activity
Activity Predecessor Time
A -- 4
B -- 8
C -- 3
D A 3
E A 6
F C 5
G B, D 6
1. Draw a network for this project.
2. Identify the critical path.
3. What is the project completion time?