Identify the critical path earliest start and finish


Assignment

Each student should complete the following problem and submit a single file in Word or Excel with all requirements in either format.

Given the following information about a small project,

Task     Duration         Immediate
           Estimates        Predecessors
A          2 days              None
B          5 days              A
C          1 day               B
D          2 days              A
E          3 days              B & D
F          12 days            E  & C

1. Draw a network diagram.
2. Identify the critical path, earliest start and finish and slack for each task.
3. Using MS Excel, produce a Gantt chart for this project.
4. What would happen if a new estimate for task D increases its expected duration from two days to six days? Would the project take longer? Would anything else change?

Solution Preview :

Prepared by a verified Expert
Supply Chain Management: Identify the critical path earliest start and finish
Reference No:- TGS02086115

Now Priced at $30 (50% Discount)

Recommended (93%)

Rated (4.5/5)