Identify the critical path by activities and duration.
Activity Duration (Wks) Preceded by
A 5 -
B 6 -
C 2 A, B
D 1 C
E 3 C
F 4 C
G 5 D, E, F
Identify the critical path of above given activities and calculate what the elapsed time of the project would be? Determine the numbers of weeks to activity D over run by without affecting the elapsed time of the project?