Marsh and Root Construction have won the contract to widen and resurface a section of road. The site manager has identified the following tasks together with the tasks that must precede them and their anticipated durations:


(a) Construct a network to portray the project.
(b) Identify the critical path and hence ascertain the minimum duration for these roadworks.