Identify the critical issues for a lean six sigma project


Question: When trying to identify the critical issues for a Lean Six Sigma project, a Black Belt creates the following chart to identify which inputs have the greatest impact on the output. Question options: X-Y Diagram FMEA Pareto Chart Np Chart