Identify the bottleneck or process constraint


Question: Deb Samson is the owner of a company that produces glass products, suh as shower doors, table tops, and specialty windows for recreational vehicles. The process involves cutting glass into the proper shape, smoothing the edges, heat treating, and packaging. The cutting process is automated and very rapid; two minutes are required to ut a piece of glass to the proper dimensions. The smoothing, heat treating, and packaging processes require eight minutes, ten minutes, and three minutes, respectively. A simple diagram of the process is shown below.

Cutting- 2 minutes
Smoothing- 8 minutes
Heat treating- 10 minutes
Packaging- 3 minutes

Q1. Identify the bottleneck or process constraint

Q2. Calculate the throughput for an eight-hour shift

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Identify the bottleneck or process constraint
Reference No:- TGS01938360

Now Priced at $20 (50% Discount)

Recommended (98%)