Your university is holding a fund-raiser and will be hiring a band to entertain spectators. You have been selected to serve as the event project manager and have created a Work Breakdown Structure and duration estimates for the activities involved in site preparation for the event. Construct a network activity diagram based on the following information:
o Conduct both a forward and backward pass using AON notation. What is the estimated total duration for the project?
o Identify all paths through the network. Which is the critical path?
o Which activities have slack time?
o Identify all burst activities and merge activities.
Textbook: Project Management by Pinto, 5th edition. ISBN: 9780134730332.
The response must include a reference list. Using Times New Roman 12 pnt font, double-space, one-inch margins, and APA style of writing and citations.