This assignment has two separate problems. Complete the following problems and submit the file (in MS Word format) to the appropriate D2L drop box for this assignment. You must show me your work (computations) in this document in order to earn the credit. Handwriting on the screen or uploading a photo of handwritten work is unacceptable. I expect you to use the editing capabilities of MS Word to complete this problem -- I must be able to evaluate your responses. Do not change the filename
(425Problem10.docx). When you submit the file to the dropbox, D2L will add your name to the filename.
1. Using the information in the following project diagram where deterministic times are in days:
a) Complete the following table.
Activity
|
Time
|
ES
|
LS
|
EF
|
LF
|
Slack
|
Critical Path (y/n)
|
A
|
|
|
|
|
|
|
|
B
|
|
|
|
|
|
|
|
C
|
|
|
|
|
|
|
|
0
|
|
|
|
|
|
|
|
E
|
|
|
|
|
|
|
|
F
|
|
|
|
|
|
|
|
G
|
|
|
|
|
|
|
|
H
|
|
|
|
|
|
|
|
I
|
|
|
|
|
|
|
|
b) Identify all paths, their expected times, and total slack for each path in the project and specify the critical path. What is the expected project duration?
2. zBull Dozier, Project Superintendent for the Carefully Planned Monuments (CPM) Co., is about to begin a project comprised of the following six activities:
ACTIVITY
|
PRECEDED BY
|
TIME ESTIMATES (days)
|
OPTIMISTIC
|
MOST LIKELY
|
PESSIMISTIC
|
A
|
---
|
38
|
50
|
62
|
B
|
---
|
90
|
99
|
108
|
C
|
---
|
85
|
100
|
115
|
D
|
A
|
19
|
25
|
31
|
E
|
B
|
91
|
100
|
115
|
F
|
D
|
62
|
65
|
68
|
Complete the tables below.
Activity
|
Mean
|
Variance
|
A
|
|
|
B
|
|
|
C
|
|
|
D
|
|
|
E
|
|
|
F
|
|
|
Path
|
Expected Time
|
Std Deviation
|
z-value
|
Path Probability of Completion
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
What is the probability that this project will be completed within 205 days?