MS PROJECT EXERCISE
The following project contains the list of activities along with their required times of completion
Activity No Activity
1 Collect Requirements
|
Time(Weeks)
2
|
Immediate Predecessors
|
2
|
Analyze processes
|
3
|
1
|
3
|
Analyze data
|
3
|
2
|
4
|
Design processes
|
7
|
2
|
5
|
Design data
|
6
|
2
|
6
|
Design screens
|
1
|
3,4
|
7
|
Design reports
|
5
|
4,5
|
8
|
Program
|
4
|
6,7
|
9
|
Test and document
|
8
|
7
|
10
|
Install
|
2
|
8,9
|
Construct a GANTT chart
What is the earliest completion time?
See the critical path
What would happen if activity 6 took 6 weeks instead of 1 week? Convert to a Network diagram
See the critical path in red.
Case : Assessing The Value and Impact of CPOE
Discussion Questions
1. How might you evaluate the CPOE implementation process at University Health Care System? Give examples of different methods or strategies you might employ.
2. How would you respond to the board's desire for a "return on investment" from this initiative? Is it a reasonable request? Why or why not?