How would a project manager use the cpi what are the


Please answer the following questions. Your responses should be between 100 and 150 words-

Questions:

1. How does a Tracking Gantt chart help communicate project progress?

2. How does earned value give a clearer picture of the project schedule and cost status than a simple plan versus actual system?

3. Schedule variance (SV) is in dollars and does not directly represent time. Why is it still useful?

4. How would a project manager use the CPI?

5. What are the differences between BAC and EAC?

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: How would a project manager use the cpi what are the
Reference No:- TGS01034404

Expected delivery within 24 Hours