Question: Consider the schedule below. The project sponsor now requires the completion date to be considerably sooner than 8/4/23. If none of the task durations can be shortened, how could you reduce the overall duration of the project? Task Name Duration Start Finish Predecessors Rebranding Campaign 105 days Mon 3/13/23 Fri 8/4/23 Conduct Market Research 30 days Mon 3/13/23 Fri 4/21/23 Develop Content 30 days Mon 4/24/23 Fri 6/2/23 2 QC