Discuss the below:
Q: Jack Simpson, contract negotiator for Nebula Airframe Company, is currently involved in bidding on a follow-up government contract. In gathering cost data from the first three units, which Nebula produced under a research and development contract, he found that the first unit took 2.000 labor hours, the second took 1, 300 labor hours, and the third took 1, 220 hours. Use Exhibit In a contract for three more units, how many labor hours should Simpson plan for? (Round your answer to the nearest whole number.)