Cycle time is computed as
A) desired output divided by the daily operating time
B) daily operating time divided by the product of desired output and the sum of job times
C) the product of desired output and the sum of job times divided by daily operating time
D) daily operating time divided by the scheduled output
E) 1.00 minus station time