How to change request if cost of performance index is given


1. Linda is the project manager for large insurance company. Her present project is to organize all the paper files to match electronic structure of IT system's servers. It is not exciting project. Linda has just completed performance report for her project. Her cost of performance index (CPI) is given as .79, and her schedule performance index (SPI) is .69. Joey, her manager, has responded with change request. Explain why?

A. The project is not performing well, so a change request is submitted to the project manager
B. The project is not performing well, so a change request is made to cancel the project
C. The project is not performing well, so Joey will likely issue a change request to remove Linda from the project
D. The project is performing well, so Joey will likely be adding requirements to the project scope.

Request for Solution File

Ask an Expert for Answer!!
Project Management: How to change request if cost of performance index is given
Reference No:- TGS031942

Expected delivery within 24 Hours