Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2012 and completed in 2013. Cost and other data are presented below: Assume that Beavis uses the percentage-of-completion method for revenue recognation.
Required: Compute the amount of gross profit recognized during 2012 and 2013.