How the new task will influence the project


Question:

Imagine that you are writing technical manuals for a computer company. Halfway through the project, your team discovers that the existing manual for configuring a motherboard must be updated. Select the statement that most accurately reflects how this new task will influence the project. The time allotted for the project will need to be adjusted. The scope of the project will need to be adjusted. The cost of the project will need to be adjusted. The time, scope, and cost of the project will need to be adjusted.