Solve the below:
Q: Hotels Inc. has contracted out its towel laundering work. The lead time for the contractor is 4 days. The daily demand for clean towels at the hotel is normally distributed with a mean of 1000 and a is constant. Standard deviation of 90. Management h as set the service level at 99%. Assume the lead Find: The Reorder point. Safety stock.