How should the project manager handle the situation


Problem: A member of a testing team in an agile project works well with the project team. However, in the previous two iterations, this team member's performance was poor, and the team had difficulty meeting the iteration goals. How should the project manager handle this situation? • Allow the project team to discuss the problem with this team member. • Discuss the issue with the team member's functional manager. • Speak to the team member regarding the need to improve performance Inform the human resource (HR) department about the issue

 

Request for Solution File

Ask an Expert for Answer!!
Other Management: How should the project manager handle the situation
Reference No:- TGS03421450

Expected delivery within 24 Hours