Problem: A project manager schedules a recurring meeting with team members across different time zones. What best practice can they employ to ensure the meeting is productive? Alternate the meeting time across time zones so that all team members feel equal priority. Keep the meeting time for all team members exactly the same for the duration of the project. Keep the meeting times as early as possible for the project manager. Prioritize the stakeholder's availability when scheduling the meeting.