How project manager and project team uses the wbs


A) Determine the manner in which the project manager and project team uses the WBS to develop a reliable bottom-up estimate. Support your response with one (1) real-world example of such usage.

B) Give an example of two (2) common risks that a project manager may encounter when planning a project. For each risk identified, provide a possible preventive action or response.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: How project manager and project team uses the wbs
Reference No:- TGS0513219

Expected delivery within 24 Hours