Based on a flexible budget for 5,000 machine hours of activity a company budgeted $25,000 for variable manufacturing overhead and $10,000 for fixed manufacturing overhead. If the company prepared a budget for 10,000 machine hours, how much total overhead would be budgeted?
a) $60,000
b) $70,000
c) $45,000
d) $50,000