Required information
[The following information applies to the questions displayed below.]
Angle Max Industries produces a product which goes through two operations, Assembly and Finishing, before it is ready to be shipped. Next year's expected costs and activities are shown below.
Assembly Finishing
Direct labor hours 220,000DLH 152,000DLH
Machine hours 420,000MH 50,400MH
Overhead costs $420,000 $638,400
Assume that the Assembly Department allocates overhead based on machine hours, and the Finishing Department allocates overhead based on direct labor hours. How much total overhead will be assigned to a product that requires 1 direct labor hour and 3.7 machine hours in the Assembly Department, and 4.5 direct labor hours and 0.3 machine hours in the Finishing Department?