A civil engineering consulting firm needs to purchase $400,000 (constant-value dollar) worth of software 5 years from now. The market interest rate is 10% and the inflation rate is 2.5%. How much should be set aside each year for 5 years? What is the payback period? Why is it not a suitable measure for project election?