Green Co. has signed a long-contract to build a new sports arena. The total revenue related to the contract is $520 million. Estimated costs for the building the arena are $180 million in the first year and $130 million in both the second and third year. The costs cannot be reasonably estimated. How much revenue should Green Co. report in their first year under iGAAP.