Kapoor Corporation uses the following activity rates from its activity-based costing to assign overhead costs to products.
Activity Cost Pools |
Activity Rate |
Setting up batches |
$ |
95.45 |
per batch |
Assembling products |
$ |
8.75 |
per assembly hour |
Processing customers orders |
$ |
51.38 |
per customer order |
Data concerning two products appear below:
Product J00A |
Product S06U |
Number of batches |
37 |
46 |
Number of assembly hours |
177 |
895 |
Number of customer orders |
20 |
39 |
Required:
a. How much overhead cost would be assigned to Product J00A using the company's activity-based costing system? (Round your answer to 2 decimal places. Omit the "$" sign in your response.)
b. How much overhead cost would be assigned to Product S06U using the company's activity-based costing system?(Round your answer to 2 decimal places. Omit the "$" sign in your response.)