How much overhead cost is allocated to the order


Capizzi Corporation has an activity-based costing system with three activity cost pools-Machining, Order Filling, and Other. In the first stage allocations, costs in the two overhead accounts, equipment depreciation and supervisory expense, are allocated to three activity cost pools based on resource consumption. Data used in the first stage allocations follow:

Overhead costs:
Equipment depreciation $83,100
Supervisory expense $2,300  
Distribution of Resource Consumption Across Activity Cost Pools:

Activity Cost Pools


Machining Order Filling Other
Equipment depreciation 0.50      0.20         0.30    
Supervisory expense 0.50      0.10         0.40    

Machining costs are assigned to products using machine-hours (MHs) and Order Filling costs are assigned to products using the number of orders. The costs in the Other activity cost pool are not assigned to products. Activity data for the company's two products follow:

  Activity:


MHs (Machining) Orders
Product Y7 1,550           770            
Product V2 9,010           2,250            
Total

10,560          

3,020            

How much overhead cost is allocated to the Order Filling activity cost pool under activity-based costing?