How much must the project remit to the contractor


Problem

• Cost reimbursable contract calculation.

o A contract calls for a total payment of $800,000 with a guarantee. Essentially the contractor is guaranteed to make at least $200,000 above his costs. If the contractor can demonstrate his costs exceed $600,000, the project will pay the difference, with a $50,000 ceiling on the overage. The contractor demonstrates he spent $623,000. How much (gross) must the project remit to the contractor?

o Another option for the same contract has the contractor guaranteed to be paid his costs plus 20%, for costs that exceed $600,000. With the same initial assumption-guarantee of $800,000 gross payment (no requirement to itemize costs), but if the contractor can show that costs exceed $600,000, the project will pay $800,000 plus the costs that exceed $600,000, plus 20% of those excess costs, with a ceiling of $900,000 gross. The contractor demonstrates he spent $623,000. How much (gross) must the project remit to the contractor?

o Under option 1.b, at what dollar amount of total costs would the contractor be assuming all of the excess costs beyond that point?

o In which option did the project assume more of the risk of a cost overrun? Explain.

• Prepare a Pareto chart of the possible causes for a student to fail a final examination in a university course.

The response should include a reference list. One-inch margins, Using Times New Roman 12 pnt font, double-space and APA style of writing and citations.

Solution Preview :

Prepared by a verified Expert
Project Management: How much must the project remit to the contractor
Reference No:- TGS03168770

Now Priced at $25 (50% Discount)

Recommended (98%)

Rated (4.3/5)