Trip Manufacturing Company prepared a static budget of 40,000 direct labor hours, with estimated overhead cost of $200,000 for variable overhead and $60,000 for fixed overhead. Trip then prepared a flexible budget at 38,000 labor hours. How much is total overhead cost at this level of activity?