XYZ compay manufactures bikes. The following data forMay of the current year are available.
Quantity of direct labor used 1,400 hours
Actual rate for directlabor 16.15
perhour bicycles completed inMay 280
Standard direct labor per bicycle 5.30
hours Standard rate for directlabor 15.25
perhour Planned bicycle forMay 210
a. determine the direct labor rate and time variances.
b. How much direct labor should be debited to work inprocess