How much assembly cost is assigned to deluxe racquets


R-Ball Corporation manufactures deluxe and standard racquetball racquets. R-Ball's total overhead costs consist of assembly costs and inspection costs. The following information is available:

Cost Deluxe Standard Total Cost

Assembly 500 mach. hours 500 mach. hours $30,000
Inspections 350 150 $50,000
2,100 labor hours 1,900 labor hours

R-Ball is considering switching from one overhead rate based on labor hours to activity-based costing. Using activity-based costing, how much assembly cost is assigned to deluxe racquets?

 