Your company's manufacturing facility uses work cells. Each cell has a design capacity of 246 units per day and an effective capacity of 232 units per day; currently the average daily production is 197 units. The manager expects productivity improvements to increase output to 226 units per day. The current annual demand is 46500 units. Due to acquisitions and consolidating facilities, the forecasted demand in three years will be eight times the current demand. How many work cells should management expect to have to meet this future demand? (Assume 250 workdays per year)