Problem:
Bragg's loses $3500 in profit per week for every week the bakery is not completed.
Required:
Question 1) How many weeks will the project take if we are willing to pay crashing cost as long as it is less than $3500?
Activity Predecessor N. Time(weeks) Crash Time(weeks) Expediting Cost/Week
A --- 9 6 $3000
B A 8 5 3500
C A 15 10 4000
D B,C 5 3 2000
E C 10 6 2500
F D,E 2 1 5000
Solve the problem and show all work.