Problem:
To construct an electricity generating unit, a company has to install 60 items. One team takes on an average 30 days to install one item. A team works for 300 days/year and management wants each team to have a capacity cushion 30 days per year.
Required: How many teams have to be deployed by the company to complete the project in one year.
Solve the given numerical problem and show all work.