Problem:
Livermore Industries uses a kanban system to manage production of the KR-9 subassembly. In a ten-hour day, they use 4600 units and use containers that can hold 80 units each. It takes 70 minutes to fill and move a container of parts to the right place on the KR-9 line that is currently rated at a 15% safety factor. How many production cards are needed?