Problem: An operation has a scrap rate of 15%. As a result, 102 sellable pieces per hour are produced.
a. How many pieces per hour are produced, including scrap? (Enter your answer as a whole number.)
b. What is the potential increase in labor productivity that could be achieved by eliminating the scrap? (Enter your answer as a percentage rounded to one decimal.)