At the American Clock Company, there is a need to produce 100 red wall clocks six weeks from now, where manufacturing the red clock requires one part W and two of part X, while part X requires one part Y and two of part Z. How many parts of each type are needed to produce the 100 red wall clocks?
Number of Part W required =
Number of Part X required =
Number of Part Y required =
Number of Part Z required =
please show calculations