How many more employees will you need to achieve number


Question: Your hiring plan calls for an increase of 32,000 units per month. The average productivity rate per worker (per hour) for the production of this unit is 40 units per hour. The firm works an 8 hour day, 5 days a week, (or 160 hours a month). How many more employees will you need to achieve this number, working the same number of hours a week?