Problem
A work centre uses 900 kg of a certain material each day. The material is transported in a container that hold 27 kg each. A kanban will take an average of 0.5 day to complete a cycle. The manager has assigned a safety factor of 0.20. The plant operates on an eight-hour day. How many kanbans are needed?