How many kanban cards are needed


Discuss the below:

Q: Meritor hires a team of consultants. The consultants suggest a partial robotic automation as well as an increase in safety stock to 12.5%. Meritor implements these suggestions. the resultsis an increase in efficiency in both the fabricationof muffler assembly and the making of catalytic converters. The muffler assemblyfabrication cell now averages 16 assemblies per hour and the leadtime has been decreased to two hours response time for a batch of 10 catalytic converters. How many kanban cards are now needed?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: How many kanban cards are needed
Reference No:- TGS02058260

Expected delivery within 24 Hours