From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take?
ID Description Predecessor Time
A Identify Topic None 1
B Research Topic A 10
C Draft Paper B 4
D Edit Paper C 4
E Create Graphics C 2
F References C 1
G Final Draft D, E, F 3