From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take? Attach or insert your AON network. You may use MSP to check your work, but your submitted file should be similar to that shown in figure 6.8 of Larson & Gray.
ID
|
Description
|
Predecessor
|
Time (days)
|
A
|
Survey site
|
None
|
2
|
B
|
Install drainage
|
A
|
5
|
C
|
Install power lines
|
A
|
3
|
D
|
Excavate site
|
B, C
|
4
|
E
|
Pour foundation
|
D
|
3
|