How many critical activities have been completed


Problem: What piece of information is missing to draw a proper conclusion from the following data?

1) Planned cost for the first month of a project = $5,000.

2) Actual expenditures for the first month = 8,000. Multiple choice question. How many critical activities have been completed. How many total activities have been completed. How much work was completed for the money spent. Nothing missing, the project is $3,000 over budget.

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: How many critical activities have been completed
Reference No:- TGS03426375

Expected delivery within 24 Hours